In reply to Rob Exile Ward:
> And another that I haven't seen mentioned yet is EdF and Hinckley Point. What do you suppose the probability of that going ahead is now? Better start getting in those candles...
Unlikely , but not because of the Brexit, because it is not a good business decision for them, as it is too risky with 4 EPR being built and in trouble, they would be mad to take on another one just now. They need to catch up on the design ( which us not finished) and complete and commission at least one station ( probably Flamanville )
'Construction on a new reactor, Flamanville 3, began on 4 December 2007.The new unit is an Areva European Pressurized Reactor type.
EDF has previously said France's first EPR would cost £3.3 billionand start commercial operations in 2012, but by 2012 EDF announced that the estimated costs have escalated to £8.5 billion ($11 billion), and the completion of construction is delayed to 2016.
TheItalian power company Enel announced it was relinquishing its 12.5% stake in the project, and 5 future EPRs, so would be reimbursed its project stake of £613 million plus interest In2014 EDF announced that completion of construction was delayed to 2017 due to delays in component delivery by Areva.
In April 2015 Areva informed the French nuclear regulator, Autorit£ de s£ret£ nucl£aire (ASN), that anomalies had been detected in the reactor vessel steel, causing "lower than expected mechanical toughness values". In June 2015 multiple faults in cooling system safety valves were discovered by ASN. In September 2015 EDF announced that the estimated costs had escalated to £10.5 billion, and the start-up of the reactor was delayed to the fourth quarter of 2018.'
Brexit is of no real consequence with all these problems , but yes I have my camping gear at the ready.
Post edited at 20:01